Q1: In a lump sum contract, if something is shown on the
drawings and/or in the specifications but not included in the bill of
quantities, the contractor may face difficulties in claiming additional
payment. However, the outcome can vary based on the specific contract
provisions and circumstances. Here are a few key considerations:
1. Contractual
Agreement: The terms and conditions outlined in the contract between the client
and the contractor will determine the rights and obligations of both parties.
The contract should specify how variations, changes, or omissions are to be
handled and whether the contractor can claim additional payment for work not
included in the bill of quantities.
2. Scope of
Work: The scope of work, as defined in the contract documents, including
drawings, specifications, and bill of quantities, is crucial in determining the
contractor's obligations. If the contract clearly states that the bill of
quantities is the definitive list of items for which the contractor will be
paid, the contractor may have limited grounds to claim additional payment for
work not included in the bill of quantities.
3. Contract
Interpretation: Interpreting the contract becomes important when discrepancies
arise between the drawings, specifications, and bill of quantities. If the
contract clearly states that the drawings and specifications take precedence
over the bill of quantities or if there are ambiguities in the contract
documents, it may support the contractor's claim for additional payment.
4. Agreement
and Communication: If the client and contractor have agreed, either formally or
informally, to include certain work that is not listed in the bill of
quantities, it may strengthen the contractor's case for claiming additional
payment. Any documented agreement, change orders, or correspondence between the
parties can be valuable in supporting the claim.
5. Notice
and Documentation: It is crucial for the contractor to provide timely notice to
the client regarding any discrepancies or variations encountered during the
construction process. The contractor should document the issue, including any
additional work performed, its impact on costs and schedule, and any requests
made to the client for additional compensation. Clear and comprehensive
documentation will strengthen the contractor's position when seeking additional
payment.
In a lump sum contract, the contractor typically assumes the
risk of pricing the work accurately and accounting for all necessary items
within the bill of quantities. However, if the contract provisions and
circumstances provide a reasonable basis, such as explicit agreement or
ambiguity in the contract documents, the contractor may have grounds to claim
additional payment. Consulting legal professionals or contract specialists
familiar with the specific contract terms and governing laws is advisable in
such situations.
Q2: In a lump sum contract, if something is measured in the
bill of quantities but not shown on the drawings and/or in the specifications,
the employer typically cannot make a deduction from the contract price. Here
are some important points to consider:
1. Contractual
Agreement: The terms and conditions specified in the contract between the
employer and the contractor will govern their respective rights and
obligations. If the bill of quantities is defined as the definitive list of
items and quantities for which the contractor will be paid, the employer may
not have grounds to make a deduction for items measured in the bill of
quantities.
2. Scope of
Work: The scope of work is generally defined by the contract documents,
including the drawings, specifications, and bill of quantities. If the bill of
quantities includes specific items and quantities, the employer is expected to
pay the contract price for those items, even if they are not shown on the
drawings or specifications.
3. Contract
Interpretation: The interpretation of the contract is essential in determining
the parties' obligations. If the contract language is clear and unambiguous and
establishes that the bill of quantities takes precedence over the drawings and
specifications, the employer may not have the authority to make deductions for
items included in the bill of quantities.
4. Change
Orders: If the employer wishes to deduct or exclude items from the contract
price that are measured in the bill of quantities but not shown on the drawings
or specifications, they would generally need to follow the appropriate change
order process. A change order is a formal agreement between the employer and
the contractor that modifies the terms of the contract, including the scope and
price. Without a valid change order, the employer may not have the right to
make deductions.
It's important to note that contract provisions and local
laws can vary, so it is essential to review the specific terms of the contract
and seek legal advice if necessary. Consulting legal professionals or contract
specialists familiar with the relevant laws and contractual obligations will
help ensure a proper understanding of the rights and obligations of both the
employer and the contractor in such situations.
Q3: In a lump sum contract, if the bill of quantities
contains lower quantities than those accurately ascertained from the drawings,
the contractor typically cannot claim additional payment solely based on the
higher quantities found in the drawings. Here's why:
1. Contractual
Agreement: The terms and conditions specified in the contract govern the rights
and obligations of both parties. If the contract explicitly states that the
bill of quantities is the definitive basis for payment, the contractor may have
limited grounds to claim additional payment based on higher quantities found in
the drawings.
2. Scope of
Work: The scope of work is usually defined by the contract documents, including
the drawings, specifications, and bill of quantities. If the bill of quantities
sets out the agreed-upon quantities, it becomes the basis for determining the
contract price. Deviations between the quantities in the bill of quantities and
the drawings may not automatically entitle the contractor to additional payment.
3. Contract
Interpretation: Interpreting the contract becomes important in understanding
the parties' rights and obligations. If the contract language is clear and
unambiguous, and it establishes that the bill of quantities takes precedence
over the drawings, the contractor may not have a valid claim for additional
payment based on the higher quantities found in the drawings alone.
However, there are some exceptions or circumstances that
could potentially support a claim for additional payment:
a. Varying Scope: If the higher quantities in the drawings
indicate a change or variation in the scope of work, the contractor may be
entitled to additional payment. The contractor would need to follow the
appropriate change order process and provide proper documentation to support
the claim.
b. Ambiguous Contract Language: If the contract language is
unclear or contradictory regarding the precedence of quantities between the
bill of quantities and the drawings, it may allow for interpretation in favor
of the contractor. In such cases, legal advice and careful review of the
contract language become crucial.
It's essential to carefully review the specific terms of the
contract and consult with legal professionals or contract specialists familiar
with the governing laws and contractual obligations. They can provide guidance
on whether the contractor has a valid claim for additional payment based on the
higher quantities found in the drawings.
Q4: In a lump sum contract, if the bill of quantities
contains greater quantities than those accurately ascertained from the
drawings, the employer generally cannot make a deduction from the contract
price based solely on the lower quantities found in the drawings. Here's why:
1. Contractual
Agreement: The terms and conditions specified in the contract govern the rights
and obligations of both parties. If the contract explicitly states that the
bill of quantities is the definitive basis for payment, the employer may have
limited grounds to make deductions based on lower quantities found in the
drawings.
2. Scope of
Work: The scope of work is typically defined by the contract documents,
including the drawings, specifications, and bill of quantities. If the bill of
quantities sets out the agreed-upon quantities, it becomes the basis for determining
the contract price. Deviations between the quantities in the bill of quantities
and the drawings may not automatically justify deductions from the contract
price.
3. Contract
Interpretation: Interpreting the contract becomes important in understanding
the parties' rights and obligations. If the contract language is clear and
unambiguous and establishes that the bill of quantities takes precedence over
the drawings, the employer may not have a valid basis for making deductions
based on the lower quantities found in the drawings alone.
However, there are certain exceptions or circumstances where
the employer may be able to make deductions:
a. Varying Scope: If the lower quantities in the drawings
indicate a change or variation in the scope of work, the employer may be
justified in making deductions. Proper change order procedures would need to be
followed, and supporting documentation would be required to demonstrate the
variation and its impact on the contract price.
b. Contractual Provisions: The contract may contain specific
provisions allowing the employer to make deductions under certain
circumstances, such as when there are discrepancies between the bill of
quantities and the drawings. These provisions would need to be carefully
reviewed and interpreted to determine their applicability.
It's crucial to carefully review the specific terms of the
contract and consult with legal professionals or contract specialists familiar
with the governing laws and contractual obligations. They can provide guidance
on whether the employer has a valid basis for making deductions from the
contract price based on the lower quantities found in the drawings.
Q5: In a lump sum contract situation where a work item or
items are to be omitted entirely, and the bill of quantities includes different
quantities than those shown on the drawings, the basis for the omission would
depend on the specific provisions in the contract. Here are two possible
scenarios:
1. Contractual
Agreement: If the contract clearly defines the hierarchy or precedence between
the bill of quantities and the drawings, that provision should be followed. For
example, if the contract states that the drawings take precedence over the bill
of quantities, the quantities shown on the drawings would be the basis for the
omission. In this case, the contractor would be entitled to exclude the entire
work item or items as indicated on the drawings, even if the bill of quantities
includes different quantities.
2. Contractual
Variation: If the contract allows for variations or changes to the bill of
quantities, there may be provisions outlining the process for omitting work
items or adjusting quantities. In this case, the contract should be followed,
and the appropriate variation procedure should be followed to agree upon the
omission and its impact on the contract price.
In both scenarios, it's important to ensure that any
omissions or variations are handled in accordance with the contract provisions.
This typically involves following proper change order procedures, providing
written notice to the relevant parties, and documenting the agreed-upon changes
to the scope of work and contract price.
To determine the specific course of action in a given
contract, it is recommended to carefully review the contract provisions related
to omissions, variations, and the hierarchy between the bill of quantities and
the drawings. Seeking advice from legal professionals or contract specialists
familiar with the specific contract terms and governing laws will ensure that
the correct basis for the omission is followed and the necessary procedures are
properly executed.
Q6: In a lump sum contract situation where the bill of
quantities includes a higher or lower specification for a measured item
compared to that included in the contract specification, the contract
specification generally takes precedence and is included in the contract price.
Here's why:
1. Contractual
Agreement: The terms and conditions specified in the contract govern the rights
and obligations of both parties. The contract specification is typically the
primary document that outlines the required specifications for the project. If
there is a discrepancy between the bill of quantities and the contract
specification, the contract specification is considered the authoritative
source.
2. Scope of
Work: The scope of work, including the required specifications, is typically
defined in the contract specification. The bill of quantities provides the
quantities of the items to be measured but does not necessarily dictate the
specifications. Therefore, the contract specification is considered the basis
for determining the required specifications for the project.
3. Contract
Interpretation: Interpreting the contract becomes important in understanding
the parties' rights and obligations. If the contract language is clear and
unambiguous, and it establishes that the contract specification takes
precedence over the bill of quantities, the specifications included in the
contract specification are typically the ones included in the contract price.
In situations where there is a discrepancy between the bill
of quantities and the contract specification, it is important to address the
issue and reconcile the specifications. This may involve issuing a formal
change order to modify the contract specification or bill of quantities to
align them. The change order process typically involves documenting the
agreed-upon changes and any associated adjustments to the contract price.
It is advisable to carefully review the specific terms of
the contract and consult with legal professionals or contract specialists
familiar with the governing laws and contractual obligations. They can provide
guidance on how to address discrepancies between the bill of quantities and the
contract specification and ensure that the correct specifications are followed
and included in the contract price.