About Me

My photo
Received my early education at the Rifle Range Road (2) Primary School, Kuala Lumpur. Attended junior high school at Raja Abdullah Secondary School, Kuala Lumpur and high school at Technical Institute, Kuala Lumpur. Further study at Mara Institute of Technology (ITM), Shah Alam, Selangor and obtained Certificate in Town and Regional Planning and Diploma in Quantity Surveying. Continued study in Mara University of Technology (UiTM) and obtained Bachelor of Quantity Surveying (Honours). I am a skilled commercial manager with extensive background in-and thorough knowledge of- development, construction, maintenance and construction contracts. Also having knowledge and experience in project, facilities and property management. Experienced in developing and implementing competitive cost planning, project budgeting, cost controlling and development appraisal. Exceptional organizational, analytic and managerial skills. Career as Commercial Expert till now.

Thursday, 27 June 2013

LUMP SUM CONTRACT BASED ON DRAWINGS AND SPECIFICATION (WITHOUT QUANTITIES)

The lump sum contract associated with construction particularly in the one of the Project in Indonesia has created untold misery to contract administrators and quantity surveyors working in project management, supervision, contractor and employer. The problem is caused by a misunderstanding of the concept of lump sum contracts and the application of the principles associated with such forms of procurement. Initially the project were Lump Sum tendered based on Bill of Quantities and upon finalization of contract both the Employer and Contractor have agreed to convert the contract to a lump sum contract based on drawings and specification with modified method of measurement for interim payment process.

In principle, a lump sum contract is an agreement pursuant to which one party consents to pay another party a set amount of money for completing the work or providing the goods described in the agreement. Typically, lump sum contracts do not require contractors to provide a detailed breakdown of costs. Rather, the payment of the total contract price is linked to the contractor completing all of the work specified in the contract. For example, a software installation company may enter into a lump sum contract for installing multiple data processing systems in a building. Instead of receiving an individual fee for each system installed, the company will receive one fixed amount after it finishes installing all of the systems.

Lump sum contracts are regularly used for a variety of transactions, including construction work, consulting projects, and architectural assignments. A lump sum contract is easy to manage since payment is made only once. Generally, the lump sum contractor is paid a flat amount of amount of money after the party receiving the services or goods is given the output. For instance, under a lump sum arrangement, an architect firm is usually paid its total fee once it has supplied all the deliverable acceptable to the Employer.

The construction industry often engages in lump sum contracting. In most cases, the building owner signs a lump sum agreement with a general contractor. The general contractor then enters into separate agreements with subcontractors.

The explanation so far seems simple. Then what seems to be the problem?

The problem arises out of two major factors:


  •  The written contract;
  •  Understanding and interpretation of the written contract.
A lump sum contract is usually a written agreement, although an oral agreement may be binding in some cases. Once the contract has been signed, all parties are bound to adhere to its terms. 

A lump sum contract ordinarily details the fixed total amount to be paid to the contractor and the timeline for payment. If the contract is for services, a comprehensive description of the scope of the services to be performed by the contractor should be documented. Contracts for goods should thoroughly detail the goods to be provided, including the components, features, and characteristics that must be a part of the final deliverable.

However, all this is dictated by the terms contained in the various documents being made part of the contract. Construction contracts using standard forms like the JCT, NEC, FIDIC etc., detail a hierarchy of documents that would be referred to in the settlement of disagreements or disputes. Such documents may include the specifications and a bill of quantities amongst other things. If the bill of quantity is listed as a contract document, it is possible for the Employer to require the contractor to execute everything it has priced for in the bill.

It must be noted that a bill of quantity can contain one or more of the following items in addition to the lump sum items:

1.         Provisional Sums
2.         Items using Prime Cost Sums
3.         Provisionally described items
4.         Provisionally measured items
5.         Nominated Sub-Contractor items
6.         Nominated Supplier items
7.         Contingencies

Despite described as a lump sum contract all the above items are subject to adjustments and additions to and deletions from the bill of quantities is possible if the contract provides for variations, but no re-measurement of quantities stated in the bill of quantities will be allowed.

As a rule, construction contractors are not entitled to receive more money than the contract specifies. Items required to complete the works must generally be provided even if they have been omitted from the bill of quantities – (Williams v Fitzmaurice (1858) 3 H&N 844). Michael O’Reilly points out that if there is no mechanism in the contract for receiving payment for these extra items, the contractor will have to pay for them. This means that the contractor will have to provide what is indispensably required to fulfil its obligations under the contract.

If it is presumed that quantities do not form a term in lump sum contracts unless the contract states otherwise, the contractor will not be paid any additional payment if the quantities required to be executed are greater than stated in the bill of quantity, (Portman and Fotheringham v Pildritch (1904),Priestly v Stone (1888), Re Ford and Bemrose (1902) CA, Sharpe v San Paulo Railway Co (1873) LR 8 Ch App 597). It could therefore implied that the reverse is also true – being that if the quantities stated in such a bill of quantity are greater than what is required to be executed (as long as the item description is not changed) the contractor will be entitled to receive the full payment against that item.

Can the Employer or Engineer therefore, change the description of an item in the bill of quantities where the quantity has been over measured and attempt to re-measure and obtain the lesser quantity? Unless the contract provides to do so, definitely not! Any attempts to do so would mean introducing an element of re-measuring where the contract does not provide and this would be in breach.

In the same context, what about an item contained in the bill of quantities which is not required to be executed? Contractors always argue that being a lump sum contract they are entitled to be paid for every item in the bill of quantities regardless of requirement in the same manner that the Employer is entitled to insist upon the contractor to provide items required but missed out in the bill of quantities and that each balances with the other. In order to prove this point the contractor will need to establish that the price it has put in for such an item is in actual fact to compensate for some item missed out in the bill of quantity. The burden of such proof will rest with the contractor.

In a lump sum contract, the specifications and drawings are used to describe and identify the scope of works. BQ (or Schedule of Rates) does not use for this purpose and it is used to value variations and often times used for interim payment valuations.

My point is in a lump sum contracts, BQ does not use to describe or identify the scope of Works. The BQ is a tool we use in a lump sum contracts to calculate the Tender / Contract Price. The scope of Works is defined in the Specifications and Drawings. The Contractor’s obligation is to complete the Works in accordance with the Specifications and Drawings. The BQ may contain items which are not required to accomplish the Contractor’s obligations under the Contract.

However, the Contractor should execute any works defined in the Specifications (in most cases Specification takes precedence over the Drawings) even though such works are excluded from the BQ (and/or not shown on the Drawings).

It can be considered that, after the award, the BQ is used only for the purposes of valuation variations and interim payments, unless BQ contains provisional items which are subjected to re-measure. Further, in lump sum (without quantities) contracts, BQ is replaced by Schedule of Rates.

In conclusion, I am in the opinion that, in a lump sum contract, you can’t simply negate payment for any item in the BQ which are not defined in the Specifications and/or shown Drawings, as the BQ does not identify or describe the Scope of Works.


Under the doctrine of restitution no one is entitled to receive any payment for what he is not entitled for under a contract and the converse is also true that the employer cannot escape from paying a contractor his rightful dues under a contract.

Credit to Dr Haris Deen for the above-mentioned article.